CLIENT: UK Utility Developer
WORKS: Design and Build
Enrgy have been awarded a contract to deliver the design and build of a gas peaking plant near Newark. The twin engine 4MW project includes the design of HV, LV, controls & structures along with the supply and build of HV/LV equipment, transformers, equipment shelters and bases. The project shall also incorporate the build of a GRP Sub Station for National Grid as part of the Contestible works. The project is expected to take around 10 months to complete.
CLIENT: UK EPC
WORKS: Build
Enrgy have been awarded a contract to deliver the build of a 4MW solar farm near Crewe. The project scope incorporates all civils and electrical works including; mechanical, modules, Inverters, substations, LV&HV cabling. The project also requires the construction of a contestable brick build SPEN substation and then close co-operation with Scottish Power over the adoption of their existing assets to allow the branching into a neighbouring third party supply. The project is expected to take around 6 months to complete.
CLIENT: UK Utility Developer
WORKS: Design and Build
Enrgy have been awarded a contract to deliver the design and build of a gas peaking plant near The Wirral. The single engine 2MW project includes the design of HV, LV, controls & structures along with the supply and build of HV/LV equipment, transformers, equipment shelters and bases. The project shall also incorporate the build of a brick Sub Station for Scottish Power as part of the Contestible works. The project is expected to take around 8 months to complete.
CLIENT: UK Utility Developer
WORKS: Design and Build
Enrgy have been awarded a contract to deliver the design and build of a BESS storage plant near Bath. The Plant will provide “Ancillary Services” to National Grid and play an important role in grid stablisation to over 14,000 surrounding homes & businesses. The scope is to include the design of HV, LV, controls & structures along with the supply and build of HV/LV equipment, transformers, equipment shelters and a contestable GRP NGED substation. The project is expected to take around 7 months to complete.
CLIENT: UK Utility O&M Provider
WORKS: Re-Power Project
Enrgy have been awarded a contract to deliver a repower project to a 5MW solar farm near Cambridge. The scope includes the swapping of inverters & transformers and their associated cables, coupled with changes to G100 compliance and ancillary comms equipment. The project is expected to take around 4 months to complete. The photo represents 1 of 3 such stations swapped.
CLIENT: UK Utility Developer
WORKS: Design and Build
Enrgy have been awarded a contract to deliver the design and build of a gas peaking plant near Wrexham. The scope is to include the design of HV, LV, controls & structures along with the supply and build of HV/LV equipment, transformers, equipment shelters and bases. The project is expected to take around 8 months to complete.
CLIENT: UK Utility Developer
WORKS: Design and Build
Enrgy have been awarded a contract to deliver the design and build of a gas peaking plant near Chester. The scope is to include the design of HV, LV, controls & structures along with the supply and build HV/LV equipment, transformers, equipment shelters and bases. The project is expected to take around 6 months to complete with a large proportion of contestable civils works also being provided by Enrgy.
CLIENT: UK Utility O&M Provider
WORKS: O&M Services
Enrgy have been awarded preferred supply partner status for works in connection with the modification and swapping of end-of-life HV equipment and transformers on a variety of sites throughout the UK. Some projects will also require a design check service provided by Enrgy to ensure any new installation work meets current guidelines
CLIENT: UK Based Investor
WORKS: Micro Gas Generation
Enrgy have been awarded 2 contracts to supply and install the earthing system to gas generation plants in the north of England. Each project consists of laying approx. ½ km of 50mm copper tape connected via 80 No exothermic welds in a radial circuit to earth rods driven 4m into the ground. This buried earthing then connects to 10 items of electrical generating equipment that is certified to operate to National Grid standards. Each project takes around 1 week to complete and was completed on-time and to budget.
CLIENT: MAJOR UK EPC
WORKS: 5MW SITE BUILD
Enrgy has completed another 5MW site, this time 20 miles north of Edinburgh. The scope was to provide electrical, civils and commissioning services. An added complexity to the project was the weather conditions at the time of construction and the remote nature of the site. The works were safely delivered on time and to budget before the G59 date.
CLIENT: MAJOR UK EPC
WORKS: 5MW SITE BUILD
Enrgy has completed another 5MW site, this time near Oxford. The scope was to provide electrical, civils and commissioning services. The standard build had added complexity through the requirement to install over 9km of earthing within the site curtledge making for tricky trenching, ploughing and cabling operations. The works were safely delivered on time and to budget before the G59 date.
CLIENT: MAJOR UK EPC
WORKS: 5MW SITE BUILD
Enrgy are pleased to announce the successful completion of another 5MW project, this time in North Wales. Our scope included the civils and electrical commissioning and foundations for HV plant. The works posed significant challenges given its spread into multiple small areas, a multitude of overhead power lines, 2 No water mains running through the site, a high pressure gas main and sub-surface bedrock. These obstacles were safely overcome and the G59 date achieved.
CLIENT: MAJOR UK EPC
WORKS: O&M SERVICES
Enrgy are pleased to announce the award of further O&M services for a major UK EPC. The projects, located within the east midlands area have a combined generation power of 40MW. The works include monthly planned routines coupled with LV and HV reactive services. In addition to technical and electrical services, Enrgy are providing civils & grounds management.
CLIENT: MAJOR UK EPC
WORKS: INTER-SITE COMMUNICATION & TELEMETRY
Providing fibre and Multicore cable installation, test and commission as an urgent reactive service on a project that was approaching G59. Our client had been let-down by their intended supplier and Enrgy responded within 24hours to fault fix and commission the communications on site to enable G59 to proceed as planned and for our client to meet the FiT deadline timescales.