8 Panel, 11KV switchgear - design, supply and commission for a private generation client in Wales.

50b28bb2-d0bb-48bd-9b6b-4c5212e4248f.JPG

Enrgy engineers installing and connecting a small Aux Transformer at a gas peaking plant near Chester.

Solar panel inspection above an electrical vehicle charging forecourt in Essex.

Enrgy undertaking a transformer swap in Leicester. The original transformer was showing wear following oil testing.

1st and 2nd fix DC main cables onto a SMA repower project near Stafford.

Aerial south site.jpg

Charlbury, Oxford, 5MW new solar build

Scope – Civils, Earthing, LV Electrical, HV cable install.

IMG_4080.JPG

Exothermic welding 50mm copper tape and rods to form an earth nest around a gas generation plant at a site near to Blackpool. 

IMG_2273.JPG

Electrical team 1st and 2nd fix of LV cabling to maintain and energise a sub station. 5 MW project near Leamington Spa.

IMG_2897.JPG

14 No Screw piles. 6 No with transition steel to support a 40ft package plant container and 4 no piles for 2 no ring beams to support transformers and oil bunds. 

Enrgy D&B Gas Peaking Plant Project. 4 HV engines and 2 LV engines connected to SPEN at 11kv.

Chalgrove - HV swap.jpg

Enrgy engineers undertaking a HV equipment swap earlier are now re-connecting the HV terminations before energising

MV inverter station fire near Derby. Enrgy disposal of all equipment, civils and replacement signals, comms, LV and HV cabling routed back to new locations of SMA MVPS station.

IMG_3647.JPG

2MW Roof-mount Repower for Large UK PLC electrical wholesale warehouse, near Stoke on Trent.

Enrgy cable fault finding equipment at work finding faults on a damaged single core Aluminium cable.

Tx - recable.jpg

HV transformer cable box. Enrgy replaced HV cables, improved general cable support and re-terminated onto the bushings

IMG_4187.JPG

A truly unique project in Manchester – The CIS Tower. A 400kw solar panel cladded building 100m high. Inspection, test and fault find to ensure the 10 year old system was maintained as designed.

Hawarden - DNO slab.JPG

Enrgy providing contestable works to build a SPEN DNO base. HV ring main equipment will sit at the head of the “F” shape and a GRP enclosure will keep it all dry.

5MW solar farm repower. Replacement of all Inverters, transformers and LV distribution and commission to G100 standard.

SMA - MVPS station moments earlier craned into final location as part of a design & build repower project for a private generation client

TX recable 2.jpg

LV feeds on a 1500Kva Transformer being rectified by a Enrgy Engineer.

Enrgy’s D&B gas peaking plant project with new; supply, install and commission HV switchgear taking pride of place with BTU providing 48hr standby.

Enrgy supporting Gridserve with EICR testing to their nationwide roadside EV charging infrastructure.

A typical Enrgy design SLD for projects involving electrical design including grid studies and earthing/lightning design.

20170922_102019.jpg

Field engineer undertaking annual DC testing on a 32 way string combiner box. This 28MW site has 140 such boxes to test.

Lodge - basement pumps.JPG

A Waterlogged cable basement under HV equipment had to be fixed. Enrgy’s design and build solution was to re-seal all incoming cables and provide a well point system below basement level with automatic pumping system. Since installation the basement has remained dry.

Enrgy’s D&B BESS project incorporating 5 Tesla MegaPack’s connected at 11kv.

Enrgy build of a 4MW solar farm in Cheshire. The build only scope incuded frames, module, civils and AC DC MV electrics inc. the build and connection onto a new 11kv brick built contestable SPEN sub station and the adoption of old SPEN equipment for a third party MV neighbour connection.

Stratton - Temp Tx.jpg

Supply and install a temporary transformer c/w with all LV and HV cabling. The existing transformer had developed a fault and long lead time replacement meant a temporary transformer was the way forward.

1st and 2nd fix commissioning of MV electrical components on a 5MW ground mount near Edinburgh.

Brick build contestable DNO room provided for National Grid as part of a private generation scheme near Birmingham.

Enrgy engineer performing testing after the completion of Repowering works on a 5MW solar farm near Cambridge

St George - annual.jpg

Enrgy performing an annual survey check on the roof of FA Training headquarters for England football - St Georges

IMG_4569.JPG

Screwed piles and transition steel to support a 15t containerized package plant solution above the flood plain in weak ground on a solar farm near Dorset.

IMG_5944.JPG

Trefoils of 240mm single core AC cable running from remote distribution boards back to a central substation on a 5MW solar farm near Edinburgh

IMG_1578.JPG

HV and LV cabling installation at a 5MW project in North Wales